First phase of the construction of Košava wind farm acquired the privileged electricity producer status

Fintel Energija a.d. announced that Košava wind farm had acquired the status of a privileged producer of electricity. This formally marked the completition of the first phase of the construction of Košava wind farm consisting of 20 wind turbines with a total installed capacity of 69 MW, which will provide electricity, and which is sufficient to meet the needs of 45,000 households. The construction of the wind farm began in mid-2017 and has been in trial operation since mid-2019. The total investment amounted to 120 million eur.